PNR’s Clark Phase 2 suffers several months’ delay

The Department of Transportation (DOTr) vowed to work closely with the contractor of the Philippine National Railways (PNR) Clark Phase 2 project after it suffered several months of delay.

In a statement, the DOTr said the project, initially slated for completion in June 2024, has been delayed until June 2025 due to the delay in the turnover of the land to project contractor POSCO Engineering & Construction.

“Before the 36-hectare site was turned over by the government to POSCO, several fruit-bearing trees were cut down, causing the delay,” it said in the statement.

About 48 buildings and facilities are expected to be built by POSCO at the project site, meant to be the Clark Depot of the North-South Commuter Railway (NSCR).

“As of December 31, 2022, more than 33 percent of the planned construction has been completed,” it said.

In addition to buildings and facilities, the Clark Depot will have 33 stabling tracks to serve as the parking areas for the trains and 12 other tracks to access maintenance facilities.

The 53-kilometer PNR Clark Phase 2 is the second leg of the NSCR and will link multiple cities and municipalities in Central Luzon with Metro Manila.

Funded by the Asian Development Bank, the project is seen to cut travel time between Malolos City in Bulacan province and Clark, Pampanga province from 1.5 hours to 30 minutes.